Back Plots Phase 1

This project was the first phase in the development of the back of the site. Liverpool City Council cleared the area and we were able to develop plots 1-8. The project is now complete and the plots have been let out and are being cultivated.

In September 2006 Liverpool City Council installed a new drainage system was installed on plots 14-17 to combat some of the flooding problems.
In April 2007 Secure fencing was erected all around the site
 The plots were cleared of all rubbish and weeds
The plots were rotavated and turned into half plots
After some hard work from the new plot holders, and 150 tonnes of top soil, the plots are now looking really good